PMG201cXuất hiện trong 3 đề thi
A cost can be either variable or fixed. Which of the following statements are correct (choose 2 answers)?
Các lựa chọn
AVariable costs: These costs change with the amount of production. Examples include the cost of material, supplies, and wages.
BFixed costs: These costs do not change as production changes. Examples include the cost of setup, rent, utilities, etc.
CFixed costs: These costs change with the amount of production. Examples include the cost of material, supplies, and wages.
DVariable costs: These costs do not change as production changes. Examples include the cost of setup, rent, utilities, etc.