A project management plan should be realistic in order to be used to manage the project. Which of the following is the best method to achieve a realistic project management plan?
Các lựa chọn
AThe sponsor creates the project management plan based on input from the project manager
BThe functional manager creates the project management plan based on input from the project manager
CThe project manager creates the project management plan based on input from senior management
DThe project manager creates the project management plan based on input from the team