A project that is in the implementation phase is six weeks behind schedule. The delivery date for the product is four months away. The project is not allowed to slip the delivery date or compromise on the quality standards established for this product. Which of the following actions would bring this project back on schedule?
Các lựa chọn
AEliminate some of the requirements that have not yet been implemented.
BAdd more engineers to the project to make up for lost work.
CAsk the current developers to work overtime until the lost work is recovered.
DHire more software quality assurance personnel.