A team member tells you that her work is too creative to provide you with a fixed single estimate for the activity. You both decide to use the average labor hours (from past, similar projects) to develop a prototype. This is an example of which of the following?
Các lựa chọn
AParametric estimating
BThree-point estimating
CAnalogous estimating
DOne-point estimating