Consider a scenario in which you learn that your project is running two weeks behind schedule. How would you know if it is acceptable to be two weeks late?
Các lựa chọn
AAsk your executive management team
BIf the schedule baseline shows you are two weeks late, then it is not acceptable
CIf the team tells you the work cannot be completed any earlier than it is acceptable
DYour variance thresholds should be documented in your project management plan, look there for guidance.