Consider the following project network: • A (Duration = 3) • B (Duration = 4), depends on A • C (Duration = 2), depends on A • D (Duration = 5), depends on B and C • E (Duration = 3), depends on D \nWhat is the critical path and total project duration?
Các lựa chọn
AA → B → D → E, Duration = 15
BA → C → D → E, Duration = 13
CA → B → D → E, Duration = 15
DA → C → D → E, Duration = 14