Given the following activities: • A (2) → B (3) → D (4) • A (2) → C (5) → D (4)\nWhich statement is correct?
Các lựa chọn
ACritical path is A → B → D with duration 9
BCritical path is A → C → D with duration 11
CBoth paths are critical
DActivity C has slack time