Given Tm is the most likely of the estimated duration of the activity, To is the optimistic value and Tp is the pessimistic one. The PERT (Program Evaluation and Review Technique) analysis calculates the expected activity duration (Te) using which of the weighted average of these three estimates?
Các lựa chọn
A$Te = (Tm + 4 \times To + Tp)/6$
B$Te = (To + 4 \times Tp + Tm)/6$
C$Te = (Tp + 4 \times Tm + To)/6$
D$Te = (Tm + To + Tp)/3$