If the response you choose is to accept a risk this means that:
Các lựa chọn
AYou actively do not consider the risk but establish contingency plan.
BYou change your plans so that you eliminate the risk.
CYou change your plan so that another party will be responsible for the risk.
DYou create your plan to reduce the probability and/or the impact of the risk.