PMG201cXuất hiện trong 1 đề thi
If the response you choose is to accept a risk this means that:
Các lựa chọn
AYou change your plan so that you eliminate the risk.
BYou change your plan so that another party will be responsible for the risk.
CYou create your plan to reduce the probability and/or the impact of the risk.
DYou actively do not consider the risk but establish contingency plan.