PMG201cXuất hiện trong 4 đề thi
If the response you choose is to enhance a risk this means that:
Các lựa chọn
AYou actively do not consider the risk but establish contingency plan.
BYou add steps to your plans to make certain the opportunity is captured.
CYou change your plan so that another party will be responsible for a partial amount of ownership of the opportunity.
DYou create your plan to increase the probability and/or the impact of the opportunity.