BDI302cXuất hiện trong 1 đề thi
In which of the following situations would you NOT recommend using an agile process?
Các lựa chọn
AFor a project where change is not expected, requirements are well known, and the solution is both well known and repeatable.
BFor a project where requirements are well known but the technology and solution are unknown (i.e., changes expected in the solution).
CFor a project where the customer wants to build an e-commerce website but the development team has never done something like this before. Further, the company knows that they want to build an e-commerce website but are not sure about the functionality at this time.
DFor a project where the customer has an idea of what they want to build but is not sure of his/her exact needs.