Once the logic of a network is laid out, the project manager will conduct a forward pass and a backward pass through the network. This will provide information regarding ______ and will identify the ______.
Các lựa chọn
AResource shortages, high risk activities
BThe total duration of the project, critical path
CThe slack for each activity, high risk activities
DThe high risk activities, non-critical path