Project scope differs from product scope in that:
Các lựa chọn
AProject scope is the work that needs to be accomplished to deliver a product, service, or result.
BProject scope completion is measured against the features, functions, and product requirements.
CProduct scope completion is measured against the project management plan including all subsidiary plans.
DProduct scope is the work that needs to be accomplished to complete a project.