The project manager has just received a change request from the customer that does not affect the project schedule and is easy to complete. What should the project manager do first?
Các lựa chọn
AMake the change happen as soon as possible
BContact the project sponsor for permission
CGo to the change control board
DEvaluate the impacts on other project constraints