PMG201cXuất hiện trong 3 đề thi
The team is helping the project manager to estimate activities on their project. There are several activities they need to estimate that have not been previously done by the company. What is the best method of estimating these activities?
Các lựa chọn
ATop-down estimating
BThree-point estimating
CParametric estimating
DBottom-up estimating