There are 50 questions, and your progress of answering is shown above. \nEach side is to take one day to build, and $1,000 has been budgeted per side. The sides are planned to be completed one after the other. Today is the end of day 3. Using the following project status chart to calculate project current PV. | Activity | Day 1 | Day 2 | Day 3 | Day 4 | Status End of Day 3 | |----------|-------|-------|-------|-------|---------------------| | Side 1 | S——F | | | | Complete, spent $1,000 | | Side 2 | | S—F——PF | | | Complete, spent $900 | | Side 3 | | S—— | PS——PF | | 50% done, spent $600 | | Side 4 | | | S—— | PS——PF | 75% done, spent $600 | **Key:** S = Actual Start, F = Actual Finish, PS = Planned Start, and PF = Planned Finish
Các lựa chọn
APV = $3,000
BPV = $3,100
CPV = $2,500
DPV = $3,250
EPV = $2,650
FPV = $2,200