To calculate early start (ES) of an activity which has only one predecessor, you will
Các lựa chọn
ATake the early finish of its immediate predecessor.
BTake the early start of its immediate predecessor.
CTake the late finish of its immediate predecessor.
DTake the late start of its immediate predecessor.