To calculate late finish (LF) of an activity which has more than one successor, you will
Các lựa chọn
ATake the earliest late start of its immediate successors.
BTake the earliest early start of its immediate successors.
CTake the earliest late finish of its immediate successors.
DTake the earliest early finish of its immediate successors.