What do we mean by Velocity in agile terms?
Các lựa chọn
AIt is calculated at the team level and represents how much work a team can get done in a sprint.
BIt is calculated at the team level and represents the estimated duration of current iteration.
CIt represents actual work done in the first iteration of project.
DIt is a velocity of the individual team members, not the team.