SWR302Xuất hiện trong 1 đề thi
Which formula is correct according to the Requirements Prioritization based on value, cost, and risk?
Các lựa chọn
A$\text{Priority} = \dfrac{\text{cost }\% + \text{ risk }\%}{\text{value }\%}$
B$\text{Priority} = \dfrac{\text{risk }\% + \text{ cost }\%}{\text{value }\% + \text{ risk }\%}$
C$\text{Priority} = \dfrac{\text{risk }\% + \text{ cost }\%}{\text{value }\% + \text{ cost }\%}$
D$\text{Priority} = \dfrac{\text{value }\%}{\text{cost }\% + \text{ risk }\%}$