SWR302Xuất hiện trong 1 đề thi
Which formula is correct according to the Requirements Prioritization based on value, cost, and risk?
Các lựa chọn
APriority = $\dfrac{\text{cost }\% + \text{risk }\%}{\text{value }\%}$
BPriority = $\dfrac{\text{risk }\% + \text{cost }\%}{\text{value }\% + \text{risk }\%}$
CPriority = $\dfrac{\text{risk }\% + \text{cost }\%}{\text{value }\% + \text{cost }\%}$
DPriority = $\dfrac{\text{value }\%}{\text{cost }\% + \text{risk }\%}$