Which formula is correct according to the Requirements Prioritization based on value, cost, and risk?
Các lựa chọn
APriority = $\dfrac{cost\% + risk\%}{value\%}$
BPriority = $\dfrac{value\%}{cost\% + risk\%}$
CPriority = $\dfrac{risk\% + cost\%}{value\% + cost\%}$
DPriority = $\dfrac{risk\% + cost\%}{value\%}$