Which formula is correct according to the Requirements Prioritization based on value, cost, and risk?
Các lựa chọn
APriority = (cost % + risk %) / value %
BPriority = (risk % + cost %) / (value % + risk%)
CPriority = (risk % + cost %) / (value % + cost %)
DPriority = value % / (cost % + risk %)