SWR302Xuất hiện trong 1 đề thi
Which of following is NOT TRUE for customer involvement during the project lifecycle?
Các lựa chọn
AOn waterfall projects, customers typically dedicate considerable time up front
BOn agile projects, customers (or a product owner who represents them) are engaged continuously throughout the project
CCustomers cannot change their requirements
DOn waterfall projects, customers should also be involved later in the project during user acceptance testing, providing feedback on whether the product meets their needs