JFE301Xuất hiện trong 1 đề thi
Which of the following appropriately describes the purpose of using WBS (Work Breakdown Structure) in software development?
Các lựa chọn
ATo divide development work into small tasks in a top-down manner, thereby facilitating work management
BTo estimate development cost and place the full weight of cost management
CTo find the critical path at an early stage and focus on such a path
DTo make a work schedule in consideration of available resources