SWR302Xuất hiện trong 1 đề thi
Which of the following best describes a sprint in Agile methodology?
Các lựa chọn
AA meeting where the team discusses what went wrong in the project
BA fixed duration during which a specific set of work has to be completed and made ready for review
CThe final phase of the project where all tasks are completed
DA long, undefined period where the team works on whatever they choose