PMG201cXuất hiện trong 2 đề thi
Which of the following is the most correct statement regarding management and contingency reserves?
Các lựa chọn
ABoth of them are included into the cost baseline of the project.
BBoth of them are not included into the cost baseline of the project.
CManagement reserve is included into the cost baseline but contingency reserve is not.
DContingency reserve is included into the cost baseline but management reserve is not.