Which of the following is the most correct statement regarding management and contingency reserves?
Các lựa chọn
ABoth of them are included into the cost budget of the project.
BBoth of them are not included into the cost budget of the project.
CManagement reserve is included into cost budget but contingency reserve is not.
DContingency reserve is included into the cost budget but management reserve is not.