Which of the following statements about reaching agreement on requirements is accurate? Select two.
Các lựa chọn
ASigning off on requirements is an infallible method to prevent any changes later in the project.
BAll participants in the requirements approval process must understand what signing off implies.
CThe purpose of signing off is to freeze requirements and prevent any future modifications.
DReaching agreement on requirements ensures that both customers and developers have a shared understanding of project objectives.