PMG201cXuất hiện trong 2 đề thi
Which one of these most correctly defines management reserve?
Các lựa chọn
APer our lesson, management reserve and contingency are exactly the same.
BManagement reserve is not tied to specific work packages it is for the entire project.
CManagement reserve is tied to specific work packages.
DManagement reserve is tied to a specific milestone or event.