PMG201cXuất hiện trong 2 đề thi
Which statement is not correct?
Các lựa chọn
AProject scope is the work that needs to be accomplished to deliver a product, service, or result.
BProduct scope completion is measured against the product requirement.
CProject scope completion is measured against the project management plan and specially the project scope statement, the work breakdown structure (WBS), and the WBS dictionary.
DProduct scope is the work that needs to be accomplished to complete a project