You have a project to build a new fence. The fence will form a square. Each side is to take one day to build, and $1,000 has been budgeted per side. The sides are planned to be completed one after the other. Today is the end of day 3. \nUsing the following project status chart to calculate project current BAC: | Activity | Day 1 | Day 2 | Day 3 | Day 4 | Status End of Day 3 | |---|---|---|---|---|---| | Side 1 | S ——— F | | | | Complete, spent $1,000 | | Side 2 | | S — F ——— PF | | | Complete, spent $900 | | Side 3 | | S | PS ——— PF | | 50% done, spent $600 | | Side 4 | | | S | PS ——— PF | 75% done, spent $600 | \nKey: S = Actual Start, F = Actual Finish, PS = Planned Start, PF = Planned Finish.
Các lựa chọn
ABAC = $3,000
BBAC = $2,500
CBAC = $4,000
DBAC = $3,100
EBAC = $3,250