PMG201cXuất hiện trong 1 đề thi
You have a project to build a new fence. The fence will form a square. Each side is to take one day to build, and $1,000 has been budgeted per side. The sides are planned to be completed one after the other. Today is the end of day 3.\nUsing the following project status chart to calculate project current SV: | Activity | Day 1 | Day 2 | Day 3 | Day 4 | Status End of Day 3 | |---|---|---|---|---|---| | Side 1 | $S$ -------- $F$ | | | | Complete, spent $1,000 | | Side 2 | | $S$ -------- $PF$ | $F$ | | Complete, spent $1,200 | | Side 3 | | | $PS$ --- $S$ --- $PF$ | | 50% done, spent $600 | | Side 4 | | | | $PS$ -------- $PF$ | Not yet started | \nKey: $S$ = Actual Start, $F$ = Actual Finish, $PS$ = Planned Start, and $PF$ = Planned Finish
Các lựa chọn
ASV = $500
BSV = -$200
CSV = -$300
DSV = $300
ESV = $200
FSV = -$500